Home Project
| S.N. | Key Personal | Qualification | Designation | Experience |
|---|---|---|---|---|
| 1 | Mr. Ramesh Kumar Singh | B. Tech. (Civil, IITK), MBA | Director-Projects | 29 Years Work Experience in Construction works |
| 2 | Mr. Avadhesh Singh (IES) | B.Tech (Civil, IITK) M.Tech (Structure IITK) | Board Advisory Member | 25 Years work experience in constructions work |
| 3 | Mr. Ajay Tewari (Retd IES) | B.Tech (Civil DC), M.Tech - IID | Board Advisory Member | 39 Years work experience in Government Services |
| 4 | Mr. Virendra Prajapati | B.Tech (Civil, IITK) | Project Director | 15 years’ work experience in Construction work |
| 5 | Mr. Arun Kumar Sharm | B.E. (Civil) | Project Director | 25 Years Work experience in construction work |
| 6 | Mr. Uday N Singh | AMIE (Civil) | GM Billing | 24 Years Work experience in construction work |
| 7 | Mr. Kamla Prasad | Diploma (Civil) | Project Director | 25 Years Work experience in construction work |
| 8 | Mr. Ram Parvesh | Diploma (Electrical) | Project Coordinator | 32 Years Work experience in construction work |
| 9 | Mr. Dig Vijay Singh | B.Sc., LLB | Manager-Legal/Taxation | 10 Years Work experience in construction work |
| 10 | Mr. Animesh Verma | ICWA | Manager Accounts & Purchase | 15 Years Work experience in Accounts & Finance |
| 11 | Mr. Raj Kumar | Diploma (Civil) | Project Coordinator | 15 Years Work experience in construction work |
| 12 | Mr. Arun Kumar | Diploma (Electrical) | Services | 15 Years Work experience in construction work |
| 13 | Mr. Ram Milan Yadav | MA | Project In charge | 20 Years Work experience in construction work |
| 14 | Mr. Abhishek Rai | Diploma (Civil) | Manager-Contract/Tendering | 08 Years Work experience in construction work |
| 15 | Ms. Dipeeka | B.Tech (Civil) | Manager-Planning | 07 Years Work experience in construction work |
| 16 | Mr. A. Singh | Diploma (Architect) | Architect | 05 Years Work experience in construction work |
| 17 | Mr. Sagar Suman | B.Tech (Civil) | Project Engineer | 04 Years Work experience in construction work |
| 18 | Mr. Gagan Agarwal | MBA (Finance) | Planning Executive | 01 Year Work experience in Planning |
| 19 | Mr. Rajesh Pandey | GNIIT-NIIT (Computer) | System Engineer | 04 Years Work experience in IT |
| 20 | Mr. Aswini Kumar Verma | ITI (Mechanical) | Foreman | 06 Years Work experience in construction work |
| 21 | Mr. Manjeet | BA | Supervisor | 05 Years Work experience |
| 22 | Mr. Kamlesh | MA (Economics) | Foreman | 12 Years Work experience in construction work |
| 23 | Mr. Bhanu Pratap | MA | Supervisor | 10 Years Work experience in construction work |
| 24 | Mr. Rana Pratap | MA | Supervisor | 06 Years Work experience in construction work |
| 25 | Mr. Varun Kumar | BA | Foreman | 10 Years Work experience in construction work |
| 26 | Mr. Muskam | BA | Operator | 08 Years Work experience in construction work |
| 27 | Mr. Virendra Kumar | BA | Supervisor | 09 Years Work experience in construction work |
| 28 | Mr. Sanjeev Jha | High School | Driver | 10 Years Work experience in driving |
| 29 | Mr. Sunil | High School | Driver | 07 Years Work experience in driving |
| 30 | Mr. Santosh | High School | Time officer | 05 Years Work experience in time office work |
| S.NO. | DESCRIPTION | UNIT | QTY. | Capacity | Years/Remarks |
|---|---|---|---|---|---|
| 1 | Concreting Machineries | ||||
| a) Gamzen Mini Batching Plant | Nos. | 3 | 8 Cum per hour | 2011 & 2013 | |
| b) Concrete Mixers Machine (1 Bag Capacity) | Nos. | 10 | 1 bag cement | 2008 / 2012 / 2013 | |
| c) Vibrators with nozzles of diff. Sizes | Nos. | 28 | 2007 / 2009 / 2012 / 2015 | ||
| i) Needle Vibrators-Oil/Electric | Nos. | 5 | |||
| ii) Beam Vibrators | Nos. | 5 | |||
| iii) Slab Vibrators/Shutter Vibrator | Nos. | 10 | |||
| iv) Transit Concrete Mixer | Nos. | 2 | |||
| f) Concrete Pump | Nos. | 2 | 30 cum/hr lift 60m | ||
| g) Earth Compactor | Nos. | 5 | |||
| h) Builder Hoist/Tower Crane | Nos. | 6 | |||
| e) Mortar Mixers | Nos. | 3 | |||
| f) Batching Plant fully automatic with pump | Nos. | 1 | 30 cum/hr | 2012 | |
| 2 | Transport Equipments | ||||
| a) Bolero camper | Nos. | 2 | 2010 and 2012 | ||
| b) Motorcycle | Nos. | 8 | 2008 / 2009 / 2012 | ||
| c) Tractor with trolley | Nos. | 4 | 2007 / 2010 / 2012 | ||
| d) Water Tanker | Nos. | 2 | |||
| 3 | Workshop Equipments | ||||
| a) Welding machine | Nos. | 3 | 2008-11 | ||
| b) Gas Cutting Equipments | Set | 3 | 2008-11 | ||
| c) Bar Cutting Machine | Nos. | 6 | 2009-11 | ||
| d) Bar Bending Machine | Nos. | 6 | 2009-11 | ||
| e) Wood Cutter Machine | Nos. | 12 | 2008-11 | ||
| f) Dumpers | Nos. | 4 | Hiring | ||
| 4 | Dewatering Equipments | ||||
| a) Submersible pumps | Nos. | 6 | 2008-11 | ||
| b) Diesel Pumps - 8 HP | Nos. | 2 | 2008-11 | ||
| c) Electric monoblock pumps | Nos. | 1 | 2008-11 | ||
| d) Generator 30 KVA | Nos. | 1 | 2009-11 | ||
| e) Generator 15 KVA | Nos. | 1 | 2010-11 | ||
| f) Tulu pump | Nos. | 4 | 2008-11 | ||
| g) | |||||
| 5 | Survey Equipments | ||||
| a) Theodolite | Nos. | 4 | 2009-11 | ||
| b) C T Machine | Nos. | 1 | 2009-11 | ||
| c) Total Station | Nos. | 1 | 2009-11 | ||
| d) Auto Level & Staff | Nos. | 4 | |||
| 6 | Shuttering Materials | ||||
| a) Steel Shuttering Plate 2x3 feet- No. 4000 | SFT | 24000 | |||
| b) Scaffolding cup lock | Nos. | 10000 | |||
| c) Steel Props/Jack | Nos. | 12000 | |||
| d) Bamboo | Nos. | 12000 | |||
| e) Chahli | Nos. | 500 | |||
| 7 | Readymade site office | ||||
| a) Site office Size (10X30 feet) | Nos. | 4 | 2009 & 2012 | ||
| 8 | Road Work | ||||
| a) Wet Macadam Mix Plant | Nos. | 21 | |||
| b) Pavers finishers | Nos. | 2 | |||
| c) Road Rollers | Nos. | 2 | |||
| d) Trucks/Trippers | Nos. | 4 | |||
| e) Vibratory road roller | Nos. | 2 | |||
| 9 | Internal & External Electrical Installation | ||||
| a) Steel/Aluminium ladder 1.5m to 8m | Nos. | 10 | |||
| b) Electric Wire drawing equipments | Nos. | 5 | |||
| c) Torque wrench for nut/bolts/screw | Nos. | 15 | |||
| d) Conduit Die Set | Nos. | 2 | |||
| f) Pipe Vice | Nos. | 5 | |||
| f) Bench Vice | Nos. | 4 | |||
| g) LT Meggar-1000 volts | Nos. | 2 | |||
| h) LT Meggar-500 volts | Nos. | 3 | |||
| i) Tong Tester | Nos. | 10 | |||
| j) Multimeter | Nos. | 4 | |||
| k) Hydraulically operated crimping machine | Nos. | 3 | |||
| l) Hand operated crimping machine | Nos. | 2 | |||
| m) Earth Tester | Nos. | 4 | |||
| n) Portable Drilling machine | Nos. | 2 | |||
| o) Overhead conduit puller | Nos. | 3 | |||
| p) Core cutting Machine | Nos. | 2 | |||
| 10 | Horticulture work | ||||
| a) Matador/Pick up van | Nos. | 2 | |||
| b) Tractor with tiller and trolley | Nos. | 2 | |||
| c) Power Lawn Mover | Nos. | 2 | |||
| d) Wheel barrows (Rubber tyre) | Nos. | 2 | |||
| e) Rubber Nose Pipe | Nos. | 2 | |||
| f) Power Sprayer | Nos. | 2 |
| S.No. | Project Name | Year | Client | Project Cost Per Year (Rs.) | Remarks |
|---|---|---|---|---|---|
| 1 | JPR Balaji Infra Private Limited | 2025-26 | JPR Group | 3.50 Cr | Low Rise Building |
| 2 | U P Electricity Department Noida | 2025-26 | Government | 2.50 Cr | Cable Laying Work |
| 3 | U P Jal Nigam Haridwar Sewerage Work | 2025-27 | Jal Nigam | 4.50 Cr | Sewerage Pipe Laying work |
| 4 | VVIP Infratech Limited | 2025-26 | UP Jal Nigam - Kasganj | 5.50 Cr | OHT work |
| 5 | A R Homes Private Limited | 2025-27 | A R Homes | 11.57 Cr | Building work |
| S.No. | Project Name | Year | Client | Project Cost | Remarks |
|---|---|---|---|---|---|
| 1 | Construction of Millennium School Building, Sector-41, Noida | 2008-10 | Educomp | Rs. 5 Cr. | Project Completed |
| 2 | Construction of School Building in Sector-9, Dwarka | 2008-10 | Era Group | Rs. 2 Cr. | Project Completed |
| 3 | Construction of Millennium School Building, Lucknow (Work on Ramtech Engineers & Contractors Pvt Ltd) | 2008-10 | Educomp | Rs. 10.0 Cr. | Project Completed |
| S.No. | Project Name | Client | Period | Project Cost (Rs. Crores) | Remarks |
|---|---|---|---|---|---|
| 1 | Construction of (G+19) high rise buildings projects at Sector-121, Ajnara Homes, Noida (Cement, Steel, RMC on recoverable basis) | Ajanara Infrastructure Ltd | 2011-2014 | 30.03 Cr. | Completed |
| 2 | Construction of cooling tower in JSW Projects Ltd Bellari Karnataka | JSW Projects Ltd | 2012-2013 | 5.50 Cr. | Completed |
| 3 | Interior works of 12 nos Towers (G+12) (Finishing Work) | Belgravia Projects Pvt Ltd | 2012-2013 | 2.80 Cr. | Completed |
| 4 | Interior works of IDBI Bank in Chhattisgarh, Bihar, Orissa | IDBI Bank | 2012-13 | 1.55 Cr. | Completed |
| 5 | Construction of 48 nos flat in Kapusheda, Delhi | ARS Homes Pvt Ltd | 2013-15 | 5.76 Cr. | Completed |
| 6 | Construction of STP and RH-Pit at Dharuheda | M2K Group | 2013-14 | 1.25 Cr. | Completed |
| 7 | Wave City Center, Sector-132, Noida (Finishing Work) | Wave Group | 2015-16 | 2.76 Cr. | Completed |
| 8 | Construction of EPC project poly house 4000 sft at Rajpur, Loni, Ghaziabad | Y.P. Kasana | 2013-14 / 2015-16 | 60 Lac | Project Completed |
| S.No. | Project Name | Client | Period | Project Cost (Rs. Crores) |
|---|---|---|---|---|
| 1 | Construction of Housing Colony at Jharli, Jhajjar, Haryana | NTPC (Era Infra Engineering Ltd) | 2010-2012 | 11.03 Cr. |
| 2 | Construction of 25MW Solar Farm Power Project in Upleta-Rajkot-Gujrat (JV with Leoduct Engineering and Consultant Ltd) | Moserbaer Engineering & Construction Ltd | 2011-2012 | 35.09 Cr. |
| 3 | Construction of Housing Project in Tata Chemicals Ltd, Babrala, Badayun-UP | Tata Chemicals Limited | 2011-2012 | 13.24 Cr. |
| 4 | Construction of Road Work in Ware House Project with Arshiya International Project, Khurja (Ramtech Engineers and Contractors Pvt Ltd) | Arshiya International Ltd | 2011-12 | 10.50 Cr. |